Construction Finance Guide
How a project actually gets paid for — construction loans and draw schedules, where the rest of the capital stack comes from, the surety bonds a GC is asked to carry, and what New York law says about retainage.
This page explains general, industry-standard concepts and, where noted, a specific New York statute — it is not legal or financial advice and doesn't account for the specific terms of any contract. Confirm current requirements with a licensed attorney or lender before relying on anything here.
How a Construction Loan Works
- Construction Loan
- A short-term loan (typically 12–36 months, interest-only) that funds a project during the build itself. Unlike a standard mortgage, the full amount isn't disbursed at closing — it's drawn down in stages as work is completed and verified.
- Draw Schedule
- The agreed timetable of partial disbursements tied to construction milestones — e.g. foundation complete, framing complete, rough-ins complete. Before each draw, a lender-hired inspector typically confirms the claimed work actually happened on site.
- Interest Reserve
- A portion of the loan set aside specifically to cover interest payments during construction, since the project isn't generating income yet to service the debt itself.
- Loan-to-Cost (LTC) vs. Loan-to-Value (LTV)
- LTC measures the loan against total project cost (land + hard + soft costs) — the primary ratio lenders underwrite construction loans against. LTV measures it against the property's completed appraised value, the more familiar ratio from permanent mortgages.
- Takeout Financing
- The permanent (or longer-term) loan that pays off — 'takes out' — the construction loan once the building is complete, either a traditional permanent mortgage or, on a construction-to-permanent product, an automatic conversion of the same loan.
The Capital Stack
- Senior Construction Debt
- The primary construction loan, usually from a bank or specialty construction lender, secured by a first lien on the property — first to be repaid, and generally the largest single piece of a project's capital stack.
- Mezzanine Debt
- Financing that sits between senior debt and equity in the capital stack — higher-cost and higher-risk than senior debt, but repaid before equity holders, often used to reduce how much of a developer's own cash equity a project requires.
- Preferred Equity
- An equity investment with a fixed preferred return, paid before common equity holders but after all debt — functions similarly to mezzanine debt in the capital stack but is structured as equity, not a loan.
- Hard Money / Bridge Loan
- A short-term loan, typically asset-based rather than underwritten on borrower credit, used to move quickly (e.g. to close on a site) or bridge a gap before permanent or construction financing is in place — faster to close, at a materially higher rate than a bank construction loan.
- JV (Joint Venture) Equity
- An outside capital partner co-invests equity alongside the developer (the 'sponsor'), typically in exchange for a share of profits and some degree of control — how many ground-up NYC projects are actually capitalized above the debt layer.
Surety Bonds
- Bid Bond
- Submitted with a bid on a project, guaranteeing the contractor will honor its bid price and sign the contract if selected — protects the owner from a contractor walking away after winning.
- Performance Bond
- Guarantees the contractor will complete the project according to the contract terms. If the contractor defaults, the surety company steps in — typically by funding completion via a replacement contractor — up to the bond's face amount.
- Payment Bond
- Guarantees subcontractors and material suppliers get paid even if the general contractor fails to pay them — the mechanism that lets a sub recover from the surety instead of only the (possibly insolvent) GC. Almost always issued alongside a performance bond on public work.
- Maintenance (Warranty) Bond
- Covers defects in materials or workmanship discovered after completion, for a defined warranty period — a distinct, later-stage guarantee from the performance bond that covers the build itself.
Retainage, and New York's 5% Cap
Retainage is a percentage of each progress payment withheld until the work is substantially complete — standard practice across the industry as leverage to ensure a job actually finishes. Historically, New York owners could negotiate retainage well above 10% on private jobs. That changed with amendments to New York General Business Law §756-a and §756-c:
- Retainage on private construction contracts of $150,000 or more is capped at 5% of the contract sum — a contract clause requiring more is void.
- Retainage must be released within 30 days of final approval of the work.
- Late release accrues interest at 1% per month from the date it was due.
- A contractor may submit a final invoice upon substantial completion, as defined in the contract.
The cap took effect November 17, 2023 (S3539) and was tightened further by S5655, signed December 19, 2025, which voids — rather than merely discourages — any private-contract clause exceeding it.
Primary source: NY State Senate Bill S3539. Explainer: Holland & Knight, "New York's 5 Percent Retainage Law".
Frequently Asked Questions
- What is retainage in a construction contract?
- A percentage of each progress payment an owner withholds from a contractor (and a GC in turn withholds from subcontractors) until the work is substantially complete — leverage to ensure the job actually gets finished, and finished correctly, rather than a contractor doing 90% of the work and moving on.
- What is New York's retainage law?
- New York General Business Law §756-a and §756-c, amended by Senate Bill S3539 (effective November 17, 2023) and further tightened by S5655 (signed December 19, 2025), cap retainage at 5% of the contract sum on private construction contracts valued at $150,000 or more — any contract clause requiring more is void. Retainage must be released within 30 days of final approval of the work, and late release accrues interest at 1% per month.
- Is a performance bond the same as insurance?
- No. Insurance protects the policyholder against loss; a performance bond protects the project owner, with the surety expecting the contractor to reimburse it if the bond is drawn on. It's closer to a guaranteed line of credit than a shared-risk insurance policy.
See real, live NYC contract awards and open bids on Contract Awards and Bidding & Opportunities, or union prevailing wage rates on Wages.